|

Spa Design
When you start to work on a Spa Design project with Da Vinci Design Associates, we will take you through a very detailed step by step process. Every item of concern is addressed in our comprehensive plan for taking your vision, and turning it into a working spa. Please review the following information for an overview of our process.
Understanding Spa Interior Construction
The Spa Building Permit Process : 2 to 6 weeks
The permits required will vary in each state, county and nation. The process may take longer
than expected and cause unnecessary and expensive delays to your Project. Before
permits are approved, drawings from architects, spa designers, engineers, general and subcontractors
will be required to be submitted.
Depending on how strict the local laws are, and
the size and scope of your project, this will determine what details and drawing are needed.
The project manager or general contractor usually is responsible for the submission and
co-ordination for permits. This can be tedious and time consuming, and involves reviews
and meetings with the local officials. It is important to confirm the contractor will handle
this when reviewing the owner-contractor agreement and fee structure.
Spa Drawings Required : 3 to 4 weeks
The drawings required for submission may include, but are not limited to, the following:
A team of professionals are needed to complete a full set of drawings. This team
includes architects, spa designers, engineers and consultants.
- Architect: specializes in creating the building shells
- Interior Designer: specializes in creating the interior of the building shell
- Structural Engineer: specializes in creating the building stability and structure
- Mechanical Engineer: specializes in creating the HVAC and plumbing
- Electrical Engineer: specializes in creating electrical panel schedule, wiring,
sizing and type of electrical systems required.
- Consultants: may specialize in fire protection or lighting etc
Spa Equipment Manufacturing : 4 to 2 weeks
Spa Interior Construction : 8 to 14 weeks
A general contractor specializes in the spa construction, fabrication, means, methods,
procedures and coordination of the building shell and the interior. The general contractor
is also responsible for making sure the spa's construction conforms to the contract documents,
drawings, building codes, ordinances and other regulations.
Installation of Spa Equipment : 1 to 2 weeks
Installation is the final placement of spa furniture, fixtures and equipment. Installation may
include carpentry, scribing, assembly, connections of power and plumbing. It also
includes removal of cartons and crates for styling stations, chairs, reception desks,
pedicure units, manicure tables, dispensary items, etc….
Project Close-out : 1 to 2 weeks
This is the pre-opening phase of the project. Punch lists, training, telephone and
computer set-up, treatment room, dispensary and retail set-up takes place during this
time. The delivery of final interior details such as artwork etc…takes place.
Here is a typical Spa Project Planner
TASK |
TIME FRAME |
DATE |
Step 1 –Pre Design
1. Business plan & budget
2. Site selection
3. Negotiating lease/rental/real estate contract
4. Financing pre-approval
5. Research equipment companies
6. Research design/architectural resources |
Completed |
_________ |
Step 2 –Design Development
1. Call local building dept for lead time and
requirements for permits
2. Finalize equipment selection and pricing
3. Finalize custom cabinet drawings and pricing
4. Select general contractor
5. Finalize interior construction documents
6. Select architect/engineer
7. Obtain final approval for financing |
12 to 16 weeks |
__________ |
Step 3 –Architectural and Engineer Drawings |
3 to 4 weeks |
___________ |
Step 4 –Bid Process |
2 to 3 weeks |
___________ |
Step 5 –Permit Process
1. Contractor to submit permits for agency
approvals
2. Place equipment order |
2 to 6 weeks |
___________ |
Step 6 –Interior Construction |
8 to 14 weeks |
___________ |
Step 7 –Equipment Installation |
1 to 2 weeks |
___________ |
| Step 8 –Project Close-out
1. Final walk through
2. Move in
3. Train employees
4. Install computer equipment and telephones |
1 to 2 weeks |
___________ |
Contact Us About Spa Design
|